Kaiwera Wind Farm – 1st Blinding Pour
First pour at Kaiwera. There are 32 Towers going up and over 16,500m3 of concrete to be poured. This the 27m Sermac pump soon to been joined by the larger 37m Sermac that will handle most of the bigger pours. Pouring look to be finish around Dec 25 all going to plan.